Monday, 8 April 2013

Risk Assessment form


Task Mode Task Name Duration Start Finish
Manually Scheduled Planning the advertisement 5 days Mon 05/11/12 Fri 09/11/12
Manually Scheduled    backup plans 1 day Mon 05/11/12 Mon 05/11/12
Manually Scheduled    storyboards 1 day Tue 06/11/12 Tue 06/11/12
Manually Scheduled    scripts 1 day Wed 07/11/12 Wed 07/11/12
Manually Scheduled    mood boards 1 day Thu 08/11/12 Thu 08/11/12
Manually Scheduled    brainstorm 1 day Fri 09/11/12 Fri 09/11/12
Manually Scheduled Client meeting 1 1 day Wed 12/12/12 Wed 12/12/12
Manually Scheduled    appropriate changes to any work done before 1 day Wed 12/12/12 Wed 12/12/12
Manually Scheduled Start filming process 6 days Mon 14/01/13 Mon 21/01/13
Manually Scheduled    locations 1 day Tue 15/01/13 Tue 15/01/13
Manually Scheduled    start filming process 1 day Wed 16/01/13 Wed 16/01/13
Manually Scheduled    filming 1 day Thu 17/01/13 Thu 17/01/13
Manually Scheduled    editing 1 day Fri 18/01/13 Fri 18/01/13
Manually Scheduled Client meeting 2 1 day Fri 25/01/13 Fri 25/01/13
Manually Scheduled    appropriate changes to the filming process 1 day Fri 25/01/13 Fri 25/01/13
Manually Scheduled Client meeting 3 3 days Wed 30/01/13 Fri 01/02/13
Manually Scheduled    final meeting with client 1 day Wed 30/01/13 Wed 30/01/13
Manually Scheduled    burn DVD's and upload video to college website 1 day Fri 01/02/13 Fri 01/02/13

No comments:

Post a Comment